Project Timeline


Project Timeline
Public announcement of project March 2009
Commencing community consultation April 2009
Permitting and environmental approvals March 2009 - March 2010
Engineering June 2009 - January 2012
(95% completion)
Construction contract arrangements finalised February 2010
Financial close 2nd Quarter 2011
Field construction start 3rd Quarter 2011
Mechanical completion 4th Quarter 2013
Startup begins 1st Quarter 2014
Full production 4th Quarter 2014